Contract Details

View and manage CNT-2023-089

Metro Station Construction

CNT-2023-089

Client Contract
Active
+SAR 2,800,000 VO

Phase 2 expansion including platforms, elevators, and pedestrian tunnels

Project:Metro Station Phase 2
Client:Metro Authority
Duration:Jun 1, 2023 - Dec 31, 2024

Contract Value

SAR 42,000,000

Original: SAR 42,000,000

Progress90.0%

General Information

Contract Number

CNT-2023-089

Project

Metro Station Phase 2

Client

Metro Authority

Contract Type

client

Timeline

Start Date

Jun 1, 2023

End Date

Dec 31, 2024

Original End Date

Jun 30, 2024

Extensions

+184 days

Signed Date

May 20, 2023

Financial Summary

Original Value

SAR 42,000,000

Variations

+SAR 2,800,000

Revised Value

SAR 44,800,000

Progress

90.0%

Recent Variations

Ground Stabilization Works

VO-METRO-2024-012approved

+SAR 2,800,000

+60 days

Platform Finishing Upgrade

VO-METRO-2024-018implemented

+SAR 350,000

No time impact

Notes

FIDIC Red Book - Underground works